Construction progress

Transparent delivery.

Monthly progress
  • Work progress
  • Monthly updates
  • Photos & video
  • Completion rates
  • Current phases
  • Timeline

Monthly progress

Site updates by month.

Select a reporting month to view completion rate, site photography, and the latest drone survey.

Raft pour — Tower One

01

December 2025

Foundation & raft

Raft foundation delivered to specification. Core pit excavation complete. Site logistics and crane base installed.

Overall completion

Drone video

Drone survey — December 2025

Aerial overview of foundation programme and site logistics layout.
Core walls — level 2

02

January 2026

Core structure start

Core walls rising on Tower One. Podium slab formwork underway. MEP coordination sessions completed for lower levels.

Overall completion

Drone video

Drone survey — January 2026

First structural rise visible from aerial perspective.
Tower One — south elevation

03

February 2026

Structure floors 1–4

Tower One structural frame advancing — floors 1–4 cast. Podium slab poured. Landscape preparation begins at podium edge.

Overall completion

Drone video

Drone survey — February 2026

Structural progress and podium context from aerial survey.
Tower One — south elevation Current report

04

March 2026

Structure & MEP rough-in

Tower One current progress — core structure advancing, MEP rough-in underway on lower floors. Façade mock-up review scheduled.

Overall completion

Drone video

Drone survey — March 2026

Monthly aerial survey — full embed available at sales centre.

Progress timeline

Four-year delivery arc.

From masterplan approval to phased handover — each year marks a defined construction milestone.

  1. 2023
    Complete

    Masterplan & permits

    Design development, authority approvals, and contractor mobilisation.

  2. 2024
    Complete

    Groundworks

    Site preparation, piling programme, and enabling works across the plot.

  3. 2025
    Complete

    Foundation & core

    Raft foundation, core construction, and podium structure delivered.

  4. 2026
    In progress

    Structure rising

    Tower superstructure, MEP rough-in, and façade programme in active delivery.

Key milestones

2025 Q4

Foundation complete

Raft and core foundation delivered to specification.

2026 Q1

Structure rising

Tower One structural frame — floors 1–8 cast.

2026 Q2

MEP rough-in

Mechanical and electrical routing on active floors.

2026 Q3

Façade programme

Envelope mock-up approved — cladding sequence begins.

Play latest survey

Drone footage

Aerial site surveys.

Monthly drone captures document vertical progress, site logistics, and the evolving skyline context.

Full-resolution drone reels are available at the sales centre and in the investor brief. Clips below reflect the latest published surveys.

  • March 2026 Structure & podium context
    2:48
  • February 2026 Floors 1–4 cast
    2:31
  • January 2026 Core rise begins
    2:22
  • December 2025 Foundation complete
    2:15

Next step

Delivery is a discipline — tracked, photographed, and shared with residents and investors.